116 kWp On-Grid Rooftop Solar plant installed in Assam Downtown University

116 kWp On-Grid Rooftop Solar plant installed in Assam Downtown University

Project Information

The solar plant was commissioned dated; 12.01.2019 on the rooftop of university premises. The Plant has been installed with polycrystalline solar cells of 330 KW capacity. Total number of PV solar cells used are 354 procured from SOVAL SOLAR. Inverters of 200 kW have been stationed, procured from INVT.

Show Your
Interest

Monthly average generation of CUF is 5.97%. Commencement of IoT based SOLARMAN RMS was installed on 09.02.2019, User ID: admission@adtu.in and Password: Solar123.

Location :

Delhi

Size of Plant :

116 kWp

Date of Commissioning :

17/02/2021